UPDATE – 9/1/15
The Harding Township Department of Public Works and our sub contractor (Checcio Paving) will be performing road repairs per our comprehensive road maintenance program. We will be filling pot holes, performing pipe and drainage work, milling deficiencies and paving all milled areas with hot asphalt. Please be careful and slow down when driving on roads when roadwork signs are present to ensure the safety of your Public Works Employees and subcontractors. Please be especially careful operating a bicycle or walking on these roads.
Phase 1 – Spring – May 15, 2015
- Road surveys (Completed)
- Pot Hole Repairs (Completed)
- Develop Road work priority list (Completed)
Phase 2 – May 18, 2015 – July 31, 2015
-
Label Basins: (started)
-
Basin Repairs: (started)
- Milling and Paving:
- Post House Rd. (Completed)
- Meyersville Rd. (Completed)
- Pleasantville Rd. (between Miller Rd and Village Rd.) (Completed)
- Dicksons Mill Rd. (Completed)
- Hunter Dr. (Completed)
- Douglas Dr. (intersection) (Completed)
-
Pleasantville Rd. (between Miller Rd and Village Rd.)(Completed)
-
Dicksons Mill Rd. (Completed)
-
Kitchell Rd. (basin repairs) (Completed)
-
Meyersville Rd. (Completed)
Phase 3 – August 1, 2015 – September 30, 2015
-
Blue Mill Rd. - bridge seam.(Completed)
-
Blue Mill Rd. - shoulder by Van Beuren. (Completed)
-
Red Gate Rd. (50% Completed)
-
St Clair Rd.
- Anthony-Wayne Rd.
- Kitchell Rd. (50% Completed)
- Woodland Ave.
Line Stripping of all Municipal roads
Oil and Stone Treatment:
-
Post House Rd.
-
Meyersville Rd.
-
Anthony-Wayne Rd.
-
St Clair Rd.
-
Fawn Hill Dr.
-
Red Gate Rd.
-
Peachcroft Rd.
-
Jenks Rd
-
Blackwell Ave.
-
Line Stripping of all Municipal roads