6/20/2016 - Road Repair and Paving Update - August 2016

The Harding Township Department of Public Works and our sub contractor (Checcio Paving) will be performing road repairs per our comprehensive road maintenance program.  We will be filling pot holes, performing pipe and drainage work, milling deficiencies and paving all milled areas with hot asphalt. 

Many roads will have an Oil & Stone (seal coating) treatment. Please be careful and slow down when driving on roads when roadwork signs are present to ensure the safety of your Public Works Employees and subcontractors.  Please be especially careful operating a bicycle or walking on these roads

Phase 1 – Spring – April 29, 2016

  • Pot Hole Repairs (Completed)   
  • Shoulder/Culvert stone work (Completed)
  • Road surveys (Completed)         
  • Develop Road work priority list (Completed)
  • Basin labeling (Started)              
  • Basin repairs (Started)

Phase 2 – May 2, 2016 – July 1, 2016

  • Basin repairs (Continuing)

    • Kitchell Rd. (Started)

  • Basin labeling (Continuing)

  • Crack sealing

    • Jenks Rd.(Completed)

    • Jenks Ct. (Completed)

    • Bockoven Ln. (Completed)

    • Willow Acres. (Completed)

    • Blackwell Ave. (Completed)

    • Blackwell Pl. (Completed)

    • Featherbed Ln. (Completed)

    • Baileys Mill Rd. (Completed)

    • Spencer Pl.(Completed)

    • Douglas Rd. (Completed)

    • Van Beuren Rd. (Completed)

    • Millbrook Rd. (Completed)

    • Red Gate Rd. (Completed)

    • White Deer Ln. (Completed)

    • Hunter Dr.(Completed)

    • Fawn Hill Dr. (Completed)

    • Loantaka North. (Completed)

    • Town Hall parking lot. (Completed)

       

  • Seal Coating (Oil & Stone) STARTING THE WEEK OF JUNE 27TH (Weather Permitting)

    •  

       

  • Milling and Paving:   

    • Woodland Rd.(Completed)
    • Jenks Rd.(Completed)
  • Drainage Work:

  • Peachcroft Rd. (Completed)

  • Shalebrook Dr.(Completed)

Phase 3 – July 5, 2016 – October 30, 2016

  • Basin Labeling:

  • Basin Repairs:

    • Kitchell Rd. (Completed)

    • Shale brook Dr. (Started)

  • Milling and Paving:

  • Spencer Pl.(Completed)

  • Douglas Rd.(Completed)

  • Featherbed Ln Blackwell Ave. (only municipal portion)

  • Youngs Rd.

  • Shale Brook Dr. (Started)

  • Peachcroft rd. (Started)

  • Baileys Mill Rd. (between Lees Hill Rd & Youngs Rd.) (Started)

  • Van Beuren Rd.

  • Tigerlily Ln.

  • Pleasant Plain Rd.

  • Blue Mill Rd.(between James St. & Silver Lake)

  •  

  • Seal Coating: (July 14-15, 2016)

    • Jenks Rd. (Completed)

    • Spencer Pl.(Completed)

    • Douglas Rd.(Completed)

    • Baileys Mill Rd. (Youngs Rd. – Rt. 202)(Completed)

    • Woodland Rd.(Completed)

    • Hunter Dr.(Completed)

    • Fawn hill Dr.(Completed)

    • White Deer Ln.(Completed)

    • Loantaka North(Completed)

    •  

       

  • Crack sealing

    • Blue Mill Rd. (James St. – Silver Lake)

    • Woodland Rd

    • Meyersville Rd.

    • Sand Spring Ln.

    • Miller Rd.

    • Pleasant Plains Rd.

    • Woodland Ave.

    • Shalebrook Dr.

    • Tigerlily Ln.

    •  

  • Line Stripping of all Municipal roads.

 

 

  • Spencer Pl.

  • Douglas Rd.

  • Blackwell Ave. (only municipal portion)      

  • Van Beuren Rd.

  • Tigerlily Ln.

  • Woodland Rd.

  • Seal Coating:

     

  • Crack sealing

    • Blue Mill Rd. (James St. – Silver Lake)

    • Woodland Rd

    • Meyersville Rd.

    • Sand Spring Ln.

    • Miller Rd.

    • Pleasant Plains Rd.

    • Woodland Ave.

    • Shalebrook Dr.

    • Tigerlily Ln.

  • Line Stripping of all Municipal roads.